Our process

The steps of building a house.

A clear path from idea to home: about 10 to 15 months from agreed brief to handover for a house, including 8 to 9 months on site.

Weeks 1–6Brief, survey, ground

Design brief, topography, geotechnical and utility strategy.

Months 2–5+Design & permissions

Architect / engineering package, RE2020, permit, finance, insurance, procurement.

Site weeks 1–5Site & foundations

Site safety, excavation, bearing acceptance, reinforcement, concrete, services below slab.

Site weeks 6–13Structure & roof

Masonry / frame, lintels, floor / roof structure, waterproofing and external windows.

Site weeks 14–20First fix & envelope

MEP rough-in, pressure tests, insulation / airtightness, partitions and photographs.

Site weeks 21–32Fit-out & commissioning

Screed drying, finishes, fixtures, heat pump / ventilation, electrical and performance checks.

Site weeks 33–36Reception & follow-up

Acceptance, snag list, as-built file (DOE), training and maintenance plan.

Administrative milestones

  • Building permit: 2-month review for a detached house, 3 months for other projects, from a complete file.
  • Permit displayed on site for the whole build.
  • Site-opening declaration (DOC) before starting.
  • Declaration of completion and compliance (DAACT) at the end.

Source: service-public.fr, “Permis de construire” page checked 13 February 2026. Read the full guide →